Inventory Management
RAW MATERIAL STORE HANDLING
The objective is to
provide a systematic and effective Warehouse handling procedure , so that there
will be an adequate control of the Warehouse operations.This procedure covers
all the operations from point of receiving from vendor ,storage handling ,issuing
to production.
Raw
Material Store Handling Details
RECEIVING
Upon receiving store keeper must
ensure they have receive Supplier Delivery Order , COC and sample material
sheet.After confirm quantity is correct,store keeper need to sign the Delivery
order and stamped with date received.Afterward store keeper will be updated the
(GRN) in the Ross system , which indicate quantity , description , delivery
order no , stock balance and location.The original copy of Delivery Order will
be submit to Planner.
IN
COMING INSPECTION
Store
keeper will fill up the GRN no and total pallet receives in the supplier
delivery order. Later store keeper will send the sample material sheet , COA
and delivery order copy to QA for incoming inspection. The material for
inspection will be located in the loading bay. For normal material , once the
material was getting approved , QA inspector will paste the “ QA Passed Label”
on material and transfer status to “QOH” and For Ship To Stock (STS) material
,QA personnel will email notify and material status transfer to “QOH”.
STORAGE
Store keeper need to ensure each of
roll should have paste with “QA pass label” for normal material and (STS) for
Ship To Stock. Afterward store keeper will move the material from receiving
area to the store. Not allowed to stocking more than 7 layer.Monthly
stock count will be conducted by the Warehouse Executive and results submitted
to Planner and Finance. During stock count store keeper also need to ensure
packing condition of material whether have any damage or not.
NON
– CONFORMANCE MATERIAL
Those non – conformance materials are
waiting for final decision of QA and Planning Dept.So,it is will be kept at
quarantine area
.NON – QUALIFY MATERIAL
.NON – QUALIFY MATERIAL
Planner who order the material shall
send an email to related party (Warehouse supervisor , QA Manager , Production Manager
and Production Supervisor) for notification with specific material type ,PO
number ,quantity and the tentative arrival schedule.
The
supplier shall paste “non – qualify material” label and No any Ship To Stock
label on each roll. The delivery order shall indicate with “non – qualify
material in the remark column.Next,the planner shall get a photo from supplier
when loading to container before ship it to us.
Planner
shall share the photo to team once receive from supplier before goods delivery.
Upon
receiving , storekeeper will proceed GRN and then QA shall transfer from QC
status to QIT while storekeeper cannot pick for production usage. Over than
that ,storekeeper shall transfer physical non qualify material (QIT) to
quarantine area.
One
of the security system that company use will release the material from non
qualify material to QOH for evaluation run upon written request by Planner.
Storekeeper pick the exact requested quantity of non – quality raw material
based on PO number given by planner.
If
the non – quality material after used still have stub roll (balance
material)shall return to warehouse. Production personnel shall pack the
material with original packing (non - qualify material label) with stub roll
label.
Before receive return material from
production , storekeeper shall ensure the balance roll should have paste with
non – qualify material label. After that storekeeper shall transfer it to
quarantine area with QIT status with movement code INVQIT.Final
disposition will handle by planner.
QA
shall paste reject sticker on rejected non – qualify material which facing
quality detect during evaluation run. Production shall raise On hold form for
planner to take action. The physical on hold material shall transfer to
quarantine area with QR status. Final disposition will handle by Planner.
Finished goods formed out by non – qualify material only for testing purpose.
Whatever produced parts shall be scrap upon planner requested.
ISSUING
OF MATERIALS TO THE PRODUCTION
Base on weekly schedule Store keeper
will check in TES system by machine no to see what item need to supply.
Subsequently going to production control room and check the balance material
follow by machine line.